Trillium Health Centre
Trillium Health Centre
About Us
Quality Safe Care
Transformation
Programs & Services
Community Programs
Patient & Visitor Information
Careers
Health Information & Wellness Centre
Volunteer Opportunities
Foundation
For Physicians & Health Professionals
Newsroom
Events
Publications
Resources
Website Feedback

Donate Now

How to Use This SiteContact UsDonateSearch
Transformation  
Transformingthe Health Care Experience


Redevelopment at Trillium

Construction Update – Progress Report - December 1, 2007

Mississauga New Wing

Construction has reached the fifth level of the new inpatient wing with form work and reinforcing installations ongoing to the west section of the floor slab. Columns and shearwalls have been formed, reinforced and poured from the fourth to fifth level complete.

New walls are being formed for the service tunnel section to connect the boiler house to the new wing. Existing electrical and mechanical services are being maintained, while plans to disconnect and reconnect electrical services are underway.

Mechanical and electrical rough-in work continues on the ground and main floors as well as on portions of the second level of the new inpatient wing. Contractors anticipate reaching the top floor and final slab pour in late January or early February.

Mississauga Renovations

The second floor roof over the Cath Lab is nearing completion. Membrane protection and minor adjustments will be completed after the rooftop air handling unit has been installed. The skylight over the reception area has been installed.

The new rooftop air handling unit will be delivered in early December and will be lifted by crane. Minor traffic disruption along the north access road (from the Family Care Centre to Confederation Parkway) can be expected.

Mechanical and electrical rough-ins in the second and main floor walls and ceiling are nearing completion. Wall and ceiling framing work is complete and wall boarding is nearing completion.

A portion of the main floor corridor between the Main Entrance and the Family Care Centre was closed to enable services work above the ceiling and renovation of the corridor. The corridor will reopen in early December.

West Toronto

Mechanical and electrical rough-in work on the main floor for the Urgent Care Centre and South entrance is continuing.

Drywall finishing on the second floor’s Cancer Detection & Treatment continues, while the mechanical room air handling unit installation and ductwork is in progress.

Steelwork is being erected for the Trillium Way and the final caisson for the new Urgent Care Centre entrance canopy is being installed.

Your support and cooperation are much appreciated during this time.

 

Watch our buildings grow!

Visit the Construction Photo Web Galley

 


If you have any questions or concerns about the redevelopment projects at Trillium Health Centre, contact us at 905.848.7294 or redevelopment@thc.on.ca

Related Links
 

 
 
Copyright ©2004. Trillium Health Centre. All Rights Reserved.   |  Disclaimer and Copyright