– Progress Report - January 2, 2008
Mississauga New
Wing
Construction has
reached the sixth level of the new wing with columns and shear
walls being made on the sixth floor.
The new walls made for the service tunnel section that connect
the boiler house to the new wing have been completed. The
new boiler has been delivered and is currently being installed.
On the main and second levels, the framing of interior partitions
are in progress.
Mechanical work continues on the ground, main, and second
levels while plumbing and duct work are being installed up
to the second level.
Electrical work continues on the ground, main, second and
third levels. The backbone for the main distribution is being
installed up to the third level.
Work on the building envelope is underway. Block back-up is
progressing along the north elevation of the second level.
The top floor and final slab pour is targeted for late January
or early February.
Mississauga Renovations
The Cath Lab roof
top air handling unit has been delivered and installation
is now in progress.
Mechanical and electrical rough-ins in the second floor walls
and ceilings are nearing completion. Completed walls have
been prime painted and flooring preparation work is in progress.
The new OR Locker Rooms, which will be turned over for occupancy
in late January are nearly completed and the new lockers will
be delivered in the near future.
On the main floor; mechanical and electrical rough-in in walls
have been completed. All walls and ceilings are completed
and painted with new flooring installed throughout. Modular
furniture installation is in progress as well as commissioning
of new systems. The main floor Fracture Clinic area is scheduled
to be handed over for occupancy in late January.
West Toronto
Structural steel
framing is well advanced on the Trillium Way and second floor
Cancer Treatment Centre. Installation of the steel floor decking
is in progress on the second floor and third floor mechanical
penthouse.
T-bar ceiling and finished flooring installation is in progress
on existing second floor area.
Steel framing is completed for new the floor area in the Cancer
Detection and Treatment area over the Surgicentre and into
the Trillium Way.
Ceiling bulkhead framing and gypsum board installation is
in progress in the area adjacent to the Urgent Care Centre.
Mechanical and electrical rough-in work is well advanced on
the existing floor area. Slab on grade is also in place for
the new south entrance.
Your support and cooperation are much appreciated during this
time. Should you have any questions or concerns, please call
the redevelopment hotline at 905.848.7294.